whatsgoingonhere-8410917red-bank-bergen-broad-062320-500x332-1352236The axle-killing potholes and front-end-scraping dips are gone, and the final touches on a makeover were underway at a key Red Bank intersection Tuesday.

What’s Going On Here? Read on.

red-bank-broad-bergen-052020-500x332-9745747New light stanchions being installed last month, and the intersection as it appeared in April, 2018. (Photos by John T. Ward. Click to enlarge.)

rb-bergen-broad-041718-220x165-3613900Closing out a project that’s been talked about for at least five years, the intersection of Broad Street and East Bergen Place reached a hallelujah milestone Tuesday as a work crew poured cement for sidewalk ramps, leaving little more than cosmetic touches remaining on the punchlist.

The Monmouth County  project ties into a $1.35 million borough rebuilding of East Bergen Place from Branch Avenue to Maple Avenue that lasted a year and itself wrapped up in June, 2019.